— Project Summary

Queue ID
SOCO-IC-903
Capacity
58 MW
Technology
Solar+Battery
Status
active
Location
Liberty, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarBatterySOCOLBNL

58 MW hybrid in Liberty, GA · In queue since August 2020 · Proposed COD October 2023

58 MW

Capacity

2

Components

Solar + Battery

5y 7m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 2m

Schedule

30 months past proposed COD

Construction75%
Queue EntryAug 27, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2023-10-01

Technology
Solar43 MW · 74%
Battery15 MW · 26%
Project Details

State

GA

County

Liberty

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Fort Stewart CU 115 kV Bus

Data Source

LBNL

No news available for this project.