58 MW hybrid in Liberty, GA · In queue since August 2020 · Proposed COD October 2023
58 MW
Capacity
2
Components
Solar + Battery
5y 7m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 2m
Schedule
30 months past proposed COD
Construction75%
Queue EntryAug 27, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2023-10-01
Technology
Solar43 MW · 74%
Battery15 MW · 26%
Project Details
State
GA
County
Liberty
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Fort Stewart CU 115 kV Bus
Data Source
LBNL