— Project Summary

Queue ID
SOCO-IC-902
Capacity
76 MW
Technology
Solar+Battery
Status
active
Location
Emanuel, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

76 MW hybrid in Emanuel, GA · In queue since August 2020 · Proposed COD September 2023

76 MW

Capacity

1

Components

Solar

5y 7m

In Queue

Suspended

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 1m

Schedule

30 months past proposed COD

In Study38%
Queue EntryAug 26, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-09-30

Project Details

State

GA

County

Emanuel

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Vidalia - Wadley Primary (Black) 230 kV Line

Data Source

LBNL

No news available for this project.