400 MW hybrid in Glynn, GA · In queue since August 2020 · Proposed COD September 2023
400 MW
Capacity
2
Components
Solar + Battery
5y 7m
In Queue
Suspended
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 1m
Schedule
30 months past proposed COD
In Study38%
Queue EntryAug 26, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-09-29
Technology
Solar200 MW · 50%
Battery200 MW · 50%
Project Details
State
GA
County
Glynn
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Thalmann TS 230 kV Bus
Data Source
LBNL