— Project Summary

Queue ID
SOCO-IC-901
Capacity
400 MW
Technology
Solar+Battery
Status
active
Location
Glynn, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

400 MW hybrid in Glynn, GA · In queue since August 2020 · Proposed COD September 2023

400 MW

Capacity

2

Components

Solar + Battery

5y 7m

In Queue

Suspended

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 1m

Schedule

30 months past proposed COD

In Study38%
Queue EntryAug 26, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-09-29

Technology
Solar200 MW · 50%
Battery200 MW · 50%
Project Details

State

GA

County

Glynn

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Thalmann TS 230 kV Bus

Data Source

LBNL

No news available for this project.