BetaActiveSolarSOCOLBNL
78 MW generation in Stone, MS · In queue since August 2020 · Proposed COD March 2024
78 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 7m
Schedule
24 months past proposed COD
In Study38%
Queue EntryAug 21, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-03-28
Project Details
State
MS
County
Stone
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Hurricane Creek - Plant Watson 230 kV Line
Data Source
LBNL
No news available for this project.