— Project Summary

Queue ID
SOCO-IC-899
Capacity
78 MW
Technology
Solar
Status
active
Location
Stone, MS
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

78 MW generation in Stone, MS · In queue since August 2020 · Proposed COD March 2024

78 MW

Capacity

1

Components

Solar

5y 7m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 7m

Schedule

24 months past proposed COD

In Study38%
Queue EntryAug 21, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-03-28

Project Details

State

MS

County

Stone

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Hurricane Creek - Plant Watson 230 kV Line

Data Source

LBNL

No news available for this project.