BetaActiveSolarSOCOLBNL
80 MW generation in Wheeler, GA · In queue since July 2020 · Proposed COD April 2026
80 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 9m
Construction75%
Queue EntryJul 24, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-04-01
Project Details
State
GA
County
Wheeler
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Eastman Primary - Vidalia 115 kV Line
Data Source
LBNL
No news available for this project.