— Project Summary

Queue ID
SOCO-IC-885
Capacity
80 MW
Technology
Solar+Battery
Status
active
Location
Dallas, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

80 MW hybrid in Dallas, AL · In queue since July 2020 · Proposed COD June 2024

80 MW

Capacity

1

Components

Solar

5y 8m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 11m

Schedule

22 months past proposed COD

In Study38%
Queue EntryJul 15, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-06-01

Project Details

State

AL

County

Dallas

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

North Selma - Selma #1 115 kV Line

Data Source

LBNL

No news available for this project.