BetaActiveSolarBatterySOCOLBNL
80 MW hybrid in Dallas, AL · In queue since July 2020 · Proposed COD June 2024
80 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 11m
Schedule
22 months past proposed COD
In Study38%
Queue EntryJul 15, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
AL
County
Dallas
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
North Selma - Selma #1 115 kV Line
Data Source
LBNL
No news available for this project.