BetaActiveSolarBatterySOCOLBNL
393.6 MW hybrid in Greene, AL · In queue since April 2020 · Proposed COD January 2024
393.6 MW
Capacity
2
Components
Solar + Battery
5y 11m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 9m
Schedule
26 months past proposed COD
Construction75%
Queue EntryApr 21, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-01-31
Technology
Solar263.6 MW · 67%
Battery130 MW · 33%
Project Details
State
AL
County
Greene
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Greene County - North Selma 230 kV Line
Data Source
LBNL
No news available for this project.