BetaActiveSolarBatterySOCOLBNL
600 MW hybrid in Decatur, GA · In queue since April 2020 · Proposed COD April 2025
600 MW
Capacity
2
Components
Solar + Battery
5y 11m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5 years
Schedule
11 months past proposed COD
In Study38%
Queue EntryApr 20, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-04-30
Technology
Solar400 MW · 67%
Battery200 MW · 33%
Project Details
State
GA
County
Decatur
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Dothan Road 230 kV Substation
Data Source
LBNL