— Project Summary

Queue ID
SOCO-IC-862
Capacity
600 MW
Technology
Solar+Battery
Status
active
Location
Decatur, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

600 MW hybrid in Decatur, GA · In queue since April 2020 · Proposed COD April 2025

600 MW

Capacity

2

Components

Solar + Battery

5y 11m

In Queue

Suspended

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

5 years

Schedule

11 months past proposed COD

In Study38%
Queue EntryApr 20, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-04-30

Technology
Solar400 MW · 67%
Battery200 MW · 33%
Project Details

State

GA

County

Decatur

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Dothan Road 230 kV Substation

Data Source

LBNL

No news available for this project.