— Project Summary

Queue ID
SOCO-IC-859
Capacity
65 MW
Technology
Battery
Status
active
Location
Talbot, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveBatterySOCOLBNL

65 MW storage in Talbot, GA · In queue since April 2020 · Proposed COD May 2023

65 MW

Capacity

1

Components

Battery

5y 11m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 1m

Schedule

35 months past proposed COD

Construction75%
Queue EntryApr 7, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2023-05-03

Project Details

State

GA

County

Talbot

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Mossy Branch Substation 115 kV Bus

Data Source

LBNL

No news available for this project.