BetaActiveBatterySOCOLBNL
65 MW storage in Talbot, GA · In queue since April 2020 · Proposed COD May 2023
65 MW
Capacity
1
Components
Battery
5y 11m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 1m
Schedule
35 months past proposed COD
Construction75%
Queue EntryApr 7, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2023-05-03
Project Details
State
GA
County
Talbot
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Mossy Branch Substation 115 kV Bus
Data Source
LBNL