— Project Summary

Queue ID
SOCO-IC-839
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Sumter, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarBatterySOCOLBNL

200 MW hybrid in Sumter, GA · In queue since November 2019 · Proposed COD July 2027

200 MW

Capacity

1

Components

Solar

6y 4m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 8m

Construction75%
Queue EntryNov 15, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-07-31

Project Details

State

GA

County

Sumter

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

North Americus - Palmyra 230 kV Line

Data Source

LBNL

No news available for this project.