200 MW hybrid in Sumter, GA · In queue since November 2019 · Proposed COD July 2027
200 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 8m
Construction75%
Queue EntryNov 15, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-07-31
Project Details
State
GA
County
Sumter
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
North Americus - Palmyra 230 kV Line
Data Source
LBNL