— Project Summary

Queue ID
SOCO-IC-800
Capacity
200 MW
Technology
Solar
Status
active
Location
Taylor, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarSOCOLBNL

200 MW generation in Taylor, GA · In queue since July 2019 · Proposed COD June 2023

200 MW

Capacity

1

Components

Solar

6y 8m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 11m

Schedule

33 months past proposed COD

Construction75%
Queue EntryJul 26, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2023-06-30

Project Details

State

GA

County

Taylor

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Patsiliga Creek Substation 230 kV Bus

Data Source

LBNL

No news available for this project.