— Project Summary

Queue ID
SOCO-IC-798
Capacity
150 MW
Technology
Solar
Status
active
Location
Macon, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarSOCOLBNL

150 MW generation in Macon, GA · In queue since July 2019 · Proposed COD July 2024

150 MW

Capacity

1

Components

Solar

6y 8m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

5 years

Schedule

21 months past proposed COD

Construction75%
Queue EntryJul 11, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2024-07-01

Project Details

State

GA

County

Macon

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

North Americus - Perry 115 kV Line

Data Source

LBNL

No news available for this project.