— Project Summary

Queue ID
SOCO-IC-769
Capacity
140 MW
Technology
Solar
Status
active
Location
Oglethorpe, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarSOCOLBNL

140 MW generation in Oglethorpe, GA · In queue since December 2018 · Proposed COD June 2023

140 MW

Capacity

1

Components

Solar

7y 3m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

4y 6m

Schedule

34 months past proposed COD

Construction75%
Queue EntryDec 21, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2023-06-01

Project Details

State

GA

County

Oglethorpe

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

East Watkinsville - Russell Dam (USA) 230 kV Line

Data Source

LBNL

No news available for this project.