BetaActiveSolarSOCOLBNL
615 MW generation in Sumter, GA · In queue since September 2017 · Proposed COD July 2023
615 MW
Capacity
1
Components
Solar
8y 6m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
5y 10m
Schedule
33 months past proposed COD
Construction75%
Queue EntrySep 13, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2023-07-15
Project Details
State
GA
County
Sumter
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Fortson - North Tifton 500 kV Line
Data Source
LBNL