— Project Summary

Queue ID
SOCO-IC-616
Capacity
117.5 MW
Technology
Solar
Status
active
Location
Pierce, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarSOCOLBNL

117.5 MW generation in Pierce, GA · In queue since March 2017 · Proposed COD November 2020

117.5 MW

Capacity

1

Components

Solar

9 years

In Queue

IA Executed

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

3y 8m

Schedule

65 months past proposed COD

Construction75%
Queue EntryMar 27, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2020-11-30

Project Details

State

GA

County

Pierce

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Offerman Substation 230 kV Bus

Data Source

LBNL

No news available for this project.