BetaActiveSolarSOCOLBNL
117.5 MW generation in Pierce, GA · In queue since March 2017 · Proposed COD November 2020
117.5 MW
Capacity
1
Components
Solar
9 years
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3y 8m
Schedule
65 months past proposed COD
Construction75%
Queue EntryMar 27, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2020-11-30
Project Details
State
GA
County
Pierce
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Offerman Substation 230 kV Bus
Data Source
LBNL
No news available for this project.