BetaActiveSolarSOCOLBNL
80 MW generation in Oglethorpe, GA · In queue since September 2016 · Proposed COD March 2020
80 MW
Capacity
1
Components
Solar
9y 6m
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3y 6m
Schedule
74 months past proposed COD
Construction75%
Queue EntrySep 21, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2020-03-01
Project Details
State
GA
County
Oglethorpe
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
East Watkinsville - Russell Dam (USA) 230 kV Line
Data Source
LBNL
No news available for this project.