BetaActiveSolarSOCOLBNL
188.93 MW generation in Decatur, GA · In queue since February 2016 · Proposed COD May 2028
188.93 MW
Capacity
1
Components
Solar
10y 1m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
12y 3m
Construction75%
Queue EntryFeb 25, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-05-01
Project Details
State
GA
County
Decatur
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Farley - South Bainbridge 230 kV Line
Data Source
LBNL
No news available for this project.