— Project Summary

Queue ID
SOCO-IC-441
Capacity
188.93 MW
Technology
Solar
Status
active
Location
Decatur, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarSOCOLBNL

188.93 MW generation in Decatur, GA · In queue since February 2016 · Proposed COD May 2028

188.93 MW

Capacity

1

Components

Solar

10y 1m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

12y 3m

Construction75%
Queue EntryFeb 25, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

GA

County

Decatur

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Farley - South Bainbridge 230 kV Line

Data Source

LBNL

No news available for this project.