BetaActiveBatterySOCOLBNL
57.5 MW storage in Floyd, GA · In queue since March 2024 · Proposed COD March 2026
57.5 MW
Capacity
1
Components
Battery
2 years
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2 years
Impact Study25%
Queue EntryMar 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-30
Project Details
State
GA
County
Floyd
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Hammond SP Substation 230 kV Bus
Data Source
LBNL
No news available for this project.