— Project Summary

Queue ID
SOCO-IC-1266
Capacity
200 MW
Technology
Solar
Status
active
Location
Bullock, AL
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarSOCOLBNL

200 MW generation in Bullock, AL · In queue since March 2024 · Proposed COD November 2027

200 MW

Capacity

1

Components

Solar

2 years

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 8m

Impact Study25%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-19

Project Details

State

AL

County

Bullock

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Thurlow Dam - Union Springs 115 kV Line

Data Source

LBNL