400 MW hybrid in Laurens, GA · In queue since March 2024 · Proposed COD July 2028
400 MW
Capacity
2
Components
Solar + Battery
2 years
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 4m
Impact Study25%
Queue EntryMar 18, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-28
Technology
Solar200 MW · 50%
Battery200 MW · 50%
Project Details
State
GA
County
Laurens
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
North Dublin - Wadley Primary 230 kV Line
Data Source
LBNL