BetaActiveGasSOCOLBNL
722 MW generation in Effingham, GA · In queue since March 2024 · Proposed COD September 2029
722 MW
Capacity
1
Components
Gas
2 years
In Queue
Cluster Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 6m
Impact Study25%
Queue EntryMar 18, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-01
Project Details
State
GA
County
Effingham
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
McCall Road - West McIntosh 500 kV Line
Data Source
LBNL
No news available for this project.