— Project Summary

Queue ID
SOCO-IC-1251
Capacity
157 MW
Technology
Solar
Status
active
Location
Lee, AL
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarSOCOLBNL

157 MW generation in Lee, AL · In queue since March 2024 · Proposed COD April 2028

157 MW

Capacity

1

Components

Solar

2 years

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

Impact Study25%
Queue EntryMar 14, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

Project Details

State

AL

County

Lee

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Bartlett's Ferry - West Point 115 kV Line

Data Source

LBNL