BetaActiveSolarSOCOLBNL
157 MW generation in Lee, AL · In queue since March 2024 · Proposed COD April 2028
157 MW
Capacity
1
Components
Solar
2 years
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 1m
Impact Study25%
Queue EntryMar 14, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-01
Project Details
State
AL
County
Lee
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Bartlett's Ferry - West Point 115 kV Line
Data Source
LBNL
No news available for this project.