— Project Summary

Queue ID
SOCO-IC-1246
Capacity
86 MW
Technology
Solar+Battery
Status
active
Location
Liberty, GA
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarBatterySOCOLBNL

86 MW hybrid in Liberty, GA · In queue since February 2024 · Proposed COD February 2026

86 MW

Capacity

2

Components

Solar + Battery

2y 1m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2 years

Schedule

2 months past proposed COD

Impact Study25%
Queue EntryFeb 7, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-02-09

Technology
Solar43 MW · 50%
Battery43 MW · 50%
Project Details

State

GA

County

Liberty

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Fort Stewart CU 115 kV Bus

Data Source

LBNL

No news available for this project.