BetaActiveSolarBatterySOCOLBNL
300 MW hybrid in Marengo, AL · In queue since January 2024 · Proposed COD April 2027
300 MW
Capacity
2
Components
Solar + Battery
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 3m
Impact Study25%
Queue EntryJan 9, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Technology
Solar175 MW · 58%
Battery125 MW · 42%
Project Details
State
AL
County
Marengo
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Bassett Creek - Greene County 230 kV Line
Data Source
LBNL
No news available for this project.