— Project Summary

Queue ID
SOCO-IC-1232
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Lee, GA
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarBatterySOCOLBNL

300 MW hybrid in Lee, GA · In queue since January 2024 · Proposed COD July 2026

300 MW

Capacity

2

Components

Solar + Battery

2y 2m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 6m

Impact Study25%
Queue EntryJan 8, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-07-01

Technology
Solar200 MW · 67%
Battery100 MW · 33%
Project Details

State

GA

County

Lee

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

North Americus - Palmyra 230 kV Line

Data Source

LBNL

No news available for this project.