BetaActiveSolarBatterySOCOLBNL
300 MW hybrid in Coffee, GA · In queue since January 2024 · Proposed COD May 2026
300 MW
Capacity
2
Components
Solar + Battery
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 4m
Impact Study25%
Queue EntryJan 8, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-05-01
Technology
Solar200 MW · 67%
Battery100 MW · 33%
Project Details
State
GA
County
Coffee
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Douglas - Kettle Creek Primary 230 kV Line
Data Source
LBNL
No news available for this project.