— Project Summary

Queue ID
SOCO-IC-1224
Capacity
80 MW
Technology
Solar
Status
active
Location
Baldwin, AL
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarSOCOLBNL

80 MW generation in Baldwin, AL · In queue since January 2024 · Proposed COD April 2028

80 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 3m

Impact Study25%
Queue EntryJan 2, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

Project Details

State

AL

County

Baldwin

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Barry - Conecuh (Nextera) 230 kV Line

Data Source

LBNL