250 MW storage in Bartow, GA · In queue since December 2023 · Proposed COD June 2027
250 MW
Capacity
1
Components
Battery
2y 3m
In Queue
IA Pending
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 6m
In Study38%
Queue EntryDec 19, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-14
Project Details
State
GA
County
Bartow
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Bowen SP 230 kV Bus
Data Source
LBNL