— Project Summary

Queue ID
SOCO-IC-1214
Capacity
120 MW
Technology
Solar
Status
active
Location
Houston, AL
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarSOCOLBNL

120 MW generation in Houston, AL · In queue since December 2023 · Proposed COD September 2028

120 MW

Capacity

1

Components

Solar

2y 3m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 9m

Impact Study25%
Queue EntryDec 13, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

Project Details

State

AL

County

Houston

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Farley - Pinckard 230 kV Line

Data Source

LBNL

No news available for this project.