BetaActiveSolarSOCOLBNL
120 MW generation in Houston, AL · In queue since December 2023 · Proposed COD September 2028
120 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 9m
Impact Study25%
Queue EntryDec 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Project Details
State
AL
County
Houston
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Farley - Pinckard 230 kV Line
Data Source
LBNL
No news available for this project.