— Project Summary

Queue ID
SOCO-IC-1210
Capacity
150 MW
Technology
Battery
Status
active
Location
Walker, AL
Region
Southeast
Developer
IA Status
IA Pending

BetaActiveBatterySOCOLBNL

150 MW storage in Walker, AL · In queue since December 2023 · Proposed COD June 2026

150 MW

Capacity

1

Components

Battery

2y 3m

In Queue

IA Pending

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 6m

In Study38%
Queue EntryDec 8, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

Project Details

State

AL

County

Walker

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Goodsprings Substation 230 kV Bus

Data Source

LBNL

No news available for this project.