BetaActiveBatterySOCOLBNL
150 MW storage in Walker, AL · In queue since December 2023 · Proposed COD June 2026
150 MW
Capacity
1
Components
Battery
2y 3m
In Queue
IA Pending
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 6m
In Study38%
Queue EntryDec 8, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
AL
County
Walker
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Goodsprings Substation 230 kV Bus
Data Source
LBNL
No news available for this project.