BetaActiveSolarSOCOLBNL
200 MW generation in Jefferson, GA · In queue since November 2023 · Proposed COD June 2027
200 MW
Capacity
1
Components
Solar
2y 4m
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 7m
Impact Study25%
Queue EntryNov 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-15
Project Details
State
GA
County
Jefferson
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Rocky Creek - Wadley Primary 230 kV Line
Data Source
LBNL
No news available for this project.