— Project Summary

Queue ID
SOCO-IC-1203
Capacity
200 MW
Technology
Solar
Status
active
Location
Jasper, MS
Region
Southeast
Developer
IA Status
IA Pending

BetaActiveSolarSOCOLBNL

200 MW generation in Jasper, MS · In queue since November 2023 · Proposed COD November 2028

200 MW

Capacity

1

Components

Solar

2y 4m

In Queue

IA Pending

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5 years

In Study38%
Queue EntryNov 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-06

Project Details

State

MS

County

Jasper

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Jasper East SS Substation 230 kV Bus

Data Source

LBNL

No news available for this project.