BetaActiveSolarBatterySOCOLBNL
99 MW hybrid in Lowndes, GA · In queue since November 2023 · Proposed COD November 2025
99 MW
Capacity
2
Components
Solar + Battery
2y 4m
In Queue
IA Pending
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2 years
Schedule
5 months past proposed COD
In Study38%
Queue EntryNov 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-04
Technology
Solar49.5 MW · 50%
Battery49.5 MW · 50%
Project Details
State
GA
County
Lowndes
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Mission Pond Substation 115 kV Bus
Data Source
LBNL
No news available for this project.