— Project Summary

Queue ID
SOCO-IC-1198
Capacity
256 MW
Technology
Solar+Battery
Status
active
Location
Houston, GA
Region
Southeast
Developer
IA Status
IA Pending

BetaActiveSolarBatterySOCOLBNL

256 MW hybrid in Houston, GA · In queue since October 2023 · Proposed COD October 2025

256 MW

Capacity

2

Components

Solar + Battery

2y 5m

In Queue

IA Pending

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2 years

Schedule

5 months past proposed COD

In Study38%
Queue EntryOct 31, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-24

Technology
Solar128 MW · 50%
Battery128 MW · 50%
Project Details

State

GA

County

Houston

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Robins AFB Solar Substation 115 kV Bus

Data Source

LBNL