— Project Summary

Queue ID
SOCO-IC-1195
Capacity
200 MW
Technology
Solar
Status
active
Location
Warren, GA
Region
Southeast
Developer
IA Status
IA Pending

BetaActiveSolarSOCOLBNL

200 MW generation in Warren, GA · In queue since October 2023 · Proposed COD August 2028

200 MW

Capacity

1

Components

Solar

2y 5m

In Queue

IA Pending

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 10m

In Study38%
Queue EntryOct 27, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-15

Project Details

State

GA

County

Warren

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Sinclair Dam - Warrenton Primary 115 kV Line

Data Source

LBNL

No news available for this project.