200 MW generation in Jones, MS · In queue since October 2023 · Proposed COD August 2027
200 MW
Capacity
1
Components
Solar
2y 5m
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 10m
Impact Study25%
Queue EntryOct 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-01
Project Details
State
MS
County
Jones
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Laurel East - South Jones 230 kV Line
Data Source
LBNL