— Project Summary

Queue ID
SOCO-IC-1176
Capacity
68.5 MW
Technology
Solar
Status
active
Location
Glascock, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

68.5 MW generation in Glascock, GA · In queue since September 2023 · Proposed COD January 2028

68.5 MW

Capacity

1

Components

Solar

2y 6m

In Queue

Suspended

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

In Study38%
Queue EntrySep 26, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-01-01

Project Details

State

GA

County

Glascock

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Branch - Springhill Church 230 kV Line

Data Source

LBNL

No news available for this project.