BetaActiveSolarSOCOLBNL
68.5 MW generation in Glascock, GA · In queue since September 2023 · Proposed COD January 2028
68.5 MW
Capacity
1
Components
Solar
2y 6m
In Queue
Suspended
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 4m
In Study38%
Queue EntrySep 26, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-01
Project Details
State
GA
County
Glascock
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Branch - Springhill Church 230 kV Line
Data Source
LBNL
No news available for this project.