— Project Summary

Queue ID
SOCO-IC-1172
Capacity
127.5 MW
Technology
Solar
Status
active
Location
Jefferson, GA
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarSOCOLBNL

127.5 MW generation in Jefferson, GA · In queue since September 2023 · Proposed COD May 2027

127.5 MW

Capacity

1

Components

Solar

2y 6m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 8m

Impact Study25%
Queue EntrySep 8, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-31

Project Details

State

GA

County

Jefferson

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Sandersville #1 - Wadley Primary 230 kV LIne

Data Source

LBNL

No news available for this project.