BetaActiveBatterySOCOLBNL
500 MW storage in Douglas, GA · In queue since August 2023 · Proposed COD October 2030
500 MW
Capacity
1
Components
Battery
2y 7m
In Queue
IA Executed
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 2m
Construction75%
Queue EntryAug 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2030-10-01
Project Details
State
GA
County
Douglas
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Villa Rica Substation 500 kV Bus
Data Source
LBNL
No news available for this project.