— Project Summary

Queue ID
SOCO-IC-1162
Capacity
100 MW
Technology
Solar
Status
active
Location
Talladega, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

100 MW generation in Talladega, AL · In queue since August 2023 · Proposed COD November 2027

100 MW

Capacity

1

Components

Solar

2y 7m

In Queue

Suspended

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 3m

In Study38%
Queue EntryAug 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-01

Project Details

State

AL

County

Talladega

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Jackson Shoals - Sylacauga 115 kV Line

Data Source

LBNL

No news available for this project.