— Project Summary

Queue ID
SOCO-IC-1160
Capacity
403.1 MW
Technology
Gas
Status
active
Location
Shelby, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveGasSOCOLBNL

403.1 MW generation in Shelby, AL · In queue since August 2023 · Proposed COD June 2030

403.1 MW

Capacity

1

Components

Gas

2y 7m

In Queue

Suspended

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6y 10m

In Study38%
Queue EntryAug 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-06-01

Project Details

State

AL

County

Shelby

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Gaston SP Substation 230 kV Bus

Data Source

LBNL

No news available for this project.