BetaActiveGasSOCOLBNL
403.1 MW generation in Shelby, AL · In queue since August 2023 · Proposed COD June 2030
403.1 MW
Capacity
1
Components
Gas
2y 7m
In Queue
Suspended
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 10m
In Study38%
Queue EntryAug 1, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-01
Project Details
State
AL
County
Shelby
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Gaston SP Substation 230 kV Bus
Data Source
LBNL
No news available for this project.