— Project Summary

Queue ID
SOCO-IC-1158
Capacity
685 MW
Technology
Gas
Status
active
Location
Mobile, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveGasSOCOLBNL

685 MW generation in Mobile, AL · In queue since August 2023 · Proposed COD November 2028

685 MW

Capacity

1

Components

Gas

2y 7m

In Queue

Suspended

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 3m

In Study38%
Queue EntryAug 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

AL

County

Mobile

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Ellicott TS Substation 230 kV Bus

Data Source

LBNL

No news available for this project.