— Project Summary

Queue ID
SOCO-IC-1149
Capacity
400 MW
Technology
Solar
Status
active
Location
Mitchell, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

400 MW generation in Mitchell, GA · In queue since July 2023 · Proposed COD March 2028

400 MW

Capacity

1

Components

Solar

2y 8m

In Queue

Suspended

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 8m

In Study38%
Queue EntryJul 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-31

Project Details

State

GA

County

Mitchell

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

North Tifton - Raccoon Creek 500 kV Line

Data Source

LBNL

No news available for this project.