— Project Summary

Queue ID
SOCO-IC-1147
Capacity
500 MW
Technology
Solar
Status
active
Location
Monroe, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

500 MW generation in Monroe, GA · In queue since June 2023 · Proposed COD October 2030

500 MW

Capacity

1

Components

Solar

2y 9m

In Queue

Suspended

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7y 4m

In Study38%
Queue EntryJun 26, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-10-01

Project Details

State

GA

County

Monroe

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Ohara - Scherer 500 kV Line

Data Source

LBNL

No news available for this project.