BetaActiveSolarSOCOLBNL
500 MW generation in Monroe, GA · In queue since June 2023 · Proposed COD October 2030
500 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Suspended
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 4m
In Study38%
Queue EntryJun 26, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-10-01
Project Details
State
GA
County
Monroe
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Ohara - Scherer 500 kV Line
Data Source
LBNL
No news available for this project.