— Project Summary

Queue ID
SOCO-IC-1146
Capacity
170 MW
Technology
Solar
Status
active
Location
Stone, MS
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

170 MW generation in Stone, MS · In queue since June 2023 · Proposed COD January 2029

170 MW

Capacity

1

Components

Solar

2y 9m

In Queue

Suspended

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 7m

In Study38%
Queue EntryJun 23, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-15

Project Details

State

MS

County

Stone

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Plant Watson - Hurricane Creek 230 kV Line

Data Source

LBNL

No news available for this project.