BetaActiveSolarSOCOLBNL
170 MW generation in Stone, MS · In queue since June 2023 · Proposed COD January 2029
170 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Suspended
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 7m
In Study38%
Queue EntryJun 23, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-15
Project Details
State
MS
County
Stone
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Plant Watson - Hurricane Creek 230 kV Line
Data Source
LBNL
No news available for this project.