156 MW generation in Jasper, MS · In queue since June 2023 · Proposed COD November 2028
156 MW
Capacity
1
Components
Solar
2y 9m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 5m
Construction75%
Queue EntryJun 9, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-11-06
Project Details
State
MS
County
Jasper
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Jasper East SS Substation 230 kV Bus
Data Source
LBNL