— Project Summary

Queue ID
SOCO-IC-1144
Capacity
260 MW
Technology
Battery
Status
active
Location
Bartow, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveBatterySOCOLBNL

260 MW storage in Bartow, GA · In queue since June 2023 · Proposed COD May 2028

260 MW

Capacity

1

Components

Battery

2y 9m

In Queue

Suspended

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 11m

In Study38%
Queue EntryJun 9, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-15

Project Details

State

GA

County

Bartow

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Kingston Substation 230 kV Bus

Data Source

LBNL

No news available for this project.