BetaActiveBatterySOCOLBNL
260 MW storage in Bartow, GA · In queue since June 2023 · Proposed COD May 2028
260 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Suspended
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 11m
In Study38%
Queue EntryJun 9, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-15
Project Details
State
GA
County
Bartow
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Kingston Substation 230 kV Bus
Data Source
LBNL
No news available for this project.