BetaActiveSolarSOCOLBNL
183 MW generation in Baldwin, GA · In queue since May 2023 · Proposed COD May 2028
183 MW
Capacity
1
Components
Solar
2y 10m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5 years
Construction75%
Queue EntryMay 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-05-15
Project Details
State
GA
County
Baldwin
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Gordon - Milledgeville (White) 115 kV Line
Data Source
LBNL
No news available for this project.