— Project Summary

Queue ID
SOCO-IC-1136
Capacity
105 MW
Technology
Solar
Status
active
Location
Lincoln, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

105 MW generation in Lincoln, GA · In queue since April 2023 · Proposed COD September 2027

105 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Suspended

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 5m

In Study38%
Queue EntryApr 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

Project Details

State

GA

County

Lincoln

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Anthony Shoals - Washington 115 kV Line

Data Source

LBNL

No news available for this project.